DAVAO CITY (MindaNews / 5 Oct) – The Department of Transportation (DOTr) is undertaking a “catch-up plan” for the implementation of the first phase of the Mindanao Railway Project (MRP) amid the delays caused by the change in scope and cost of the project.
Patricia Melizza B. Ruivivar, MRP deputy manager, said in an interview on Friday that they cannot proceed with the bidding immediately because the project still needs to get the approval of the National Economic Development Authority-Investment Coordination Committee (NEDA-ICC).
The Phase 1 Tagum City-Davao City-Digos City (TDD) line needs another approval from NEDA-ICC brought about by the change in scope and cost of the project after DOTr changed it to two-track electricity-run railway instead of one-track and diesel-run locomotive.
Pending approval of the NEDA-ICC, she said the DOTr undertakes the catch-up plan, including geo-technical works from Davao City to Digos City. The Davao City-Tagum City portion has just been completed, she added.
Also, she said the 90-day parcellary survey on the affected properties affected has commenced in September 2018 and will be finished by next month.
Another preparation is the environmental survey which they expect to be completed by January 2019, so that the environmental compliance certificate will be released by February, she said.
The DOTr hopes to start the construction of Phase 1 by first quarter of next year.
“The timeline has not yet changed as far as I know. Catch up plan is being implemented the best we can,” she said.
Ruivivar said they will have to ask the Land Bank of the Philippines and Development Bank of the Philippines to appraise the values of the properties located along the path of the TDD line but the DOTr will tap the services of private appraisers if the two state-owned banks cannot commit to finish it within its desired timeframe.
She said the DOTr wants the affected properties along the 102-kilometer phase 1 appraised by December 2018.
Ruivivar previously said the Chinese Government will finance the railway project through Official Development Assistance (ODA) fund.
“It’s a done deal,” Ruivivar said in a press conference on August 31.
Phase 1 costs about P130 billion.
The budget was previously set at P36 billion, which was intended for a one-track and diesel-run locomotive.
According to DOTr, the railway’s first segment will reduce travel time from Tagum City, Davao del Norte to Digos City, Davao del Sur from 3.5 hours to 1.3 hours once it starts operating in 2022.
It added the rail line will be built with a single track, with provisions for future tracks and electrification. It will have six five-car passenger trains with three spare cars, four locomotives and 15 freight cars.
Upon project completion, the DOTr expects the daily ridership of the Tagum-Davao-Digos segment to increase to 134,060 by 2022.
The DOTr projects the daily ridership to further increase to 237,023 by 2032 and 375,134 by 2042. (Antonio L. Colina IV / MindaNews)