Aside from this, he said the almost daily rains in the last two months has slowed down the construction works at the site.
Owing to this, Gayosa said the city government extended the project’s construction period for 120 days or until Oct. 22.
“The extension was in order and there was basis for it since there were works added by the project management team based on its plan,” he said.
The terminal is being constructed in a 5.9-hectare property acquired by the city government in Purok Yellow Bell, Barangay Sta. Cruz in Koronadal City.
The city government initially spent P40 million for the purchase of the integrated terminal complex site.[]
The proposed integrated terminal’s main building was designed to cover two hectares and the rest of the site will serve as buffer area or spot for future developments.[]